What an assessment for UEPOPS075 must cover
44 assessable components: 6 elements (18 performance criteria), 15 performance evidence and 11 knowledge evidence requirements. An audit-defensible tool maps every question and task back to these — that mapping is the coverage matrix Auditori generates alongside the assessment.
Elements & performance criteria
1 Plan and prepare for switching operations
- 1.1Work health and safety (WHS)/occupational health and safety (OHS) regulations, legislative requirements, codes of practice, manufacturers’ recommendations and specifications, environmental requirements and workplace procedures are identified, applied and monitored
- 1.2Work requirements are identified from relevant personnel and documentation in accordance with workplace procedures
- 1.3Documentation to determine a.c. electrical system plant status is assessed and evaluated in accordance with workplace procedures
- 1.4Equipment inspections, preoperational checks and preparations for a.c. electrical system service are carried out in accordance with manufacturers’ recommendations and specifications, and workplace procedures
- 1.5Switchboard and electrical equipment operational prerequisites and switching sequences are established in accordance with manufacturers’ recommendations and specifications, and workplace procedures
2 Carry out operation of switchgear and switchboards
- 2.1Operation of switchgear is carried out in accordance with manufacturers’ recommendations and specifications, and workplace procedures
- 2.2Isolation, removal and reinstatement of switchgear, switchboards and rectification system is carried out, in accordance with manufacturers’ recommendations and specifications, and workplace procedures
- 2.3Paralleling and balancing requirements are assessed to meet a.c. electrical system stability in accordance with workplace procedures
- 2.4Rectification system is operated, isolated and reinstated in accordance with manufacturers’ recommendations and specifications, and workplace procedures
3 Test switchgear and equipment operation
- 3.1Operational tests are performed in accordance with workplace procedures
- 3.2Switchgear and equipment are observed for correct operational response in accordance with workplace procedures
- 3.3Switchgear equipment is returned to required operational status upon completion of testing in accordance with workplace procedures
4 Analyse a.c. electrical system, switchgear and equipment faults
- 4.1Causes of abnormal a.c. electrical system and switchgear operating conditions are identified by analysing technical and operational information in accordance with workplace procedures
- 4.2a.c. electrical system and switchgear plant integrity and personnel safety are maintained in consultation with relevant personnel, technical and operational documentation in accordance with workplace procedures
5 Inspect and monitor a.c. electrical system and switchboards
- 5.1a.c. electrical system and switchgear is monitored and inspected for normal operation and to detect deviations in accordance with workplace procedures
- 5.2Relevant personnel are notified when a.c. electrical system defects and abnormal operating conditions are detected in accordance with workplace procedures
6 Complete documentation
- 6.1a.c. electrical system equipment problems and status are reported in accordance with workplace procedures
- 6.2Documentation is updated in accordance with workplace procedures
Performance evidence
- analysing equipment, alternating current (a.c.) electrical system and protection faults using data analysis techniques and tools
- applying work health and safety (WHS)/occupational health and safety (OHS) requirements, including: - emergency procedures - risk control measures - safe working practices
- communicating with personnel
- completing documentation using recording procedures
- conducting switching operations
- identifying a.c. electrical system plant status
- implementing regulations, legislative requirements, codes of practice, manufacturers’ recommendations and specifications, and environmental requirements
- interpreting manuals
- monitoring and inspecting equipment, a.c. electrical system and protection operation
- operating switchgear and equipment
- organising resources
- preparing a.c. electrical system plant and equipment for operation
- recognising and responding to abnormal a.c. electrical system plant operating conditions
- testing a.c. electrical system plant operationally using diagnostic and test techniques
- working with permit to work system
Knowledge evidence
- a.c. electrical system plant and equipment, location and operating parameters
- a.c. electrical system plant status
- arrangements of power production plant
- manuals
- permit to work system
- regulations, legislative requirements, codes of practice, manufacturers’ recommendations and specifications, and environmental requirements
- switchgear - operation, isolation and earthing
- switching practices and procedures
- WHS/OHS requirements, including: - emergency procedures - risk control measures - safe working practices
- workplace documentation
- workplace policies and procedures
Unit content sourced from training.gov.au — © Commonwealth of Australia, licensed under CC BY 4.0. Auditori is not affiliated with the Department of Employment and Workplace Relations.
See what you get before you start
Real, unedited Auditori output (RIIHAN201E shown), branded for a sample RTO:
Questions about assessing UEPOPS075
What does an assessment tool for UEPOPS075 need to cover?
To satisfy the Principles of Assessment and Rules of Evidence, an assessment for UEPOPS075 needs to address all 44 unit components: 6 elements with 18 performance criteria, 15 performance evidence requirements, 11 knowledge evidence requirements, and the foundation skills. A coverage matrix mapping each question and task to these components is what an auditor looks for.
How does Auditori generate an assessment tool for UEPOPS075?
Auditori pulls the current release of UEPOPS075 from training.gov.au and generates a complete package: candidate assessment, assessor guide with model answers and observation criteria, and a coverage matrix mapping every component. A suitably qualified person then reviews and approves the draft in a built-in workflow — consistent with ASQA's guidance on AI use in VET — before export as branded PDF and editable Word.
Is the first assessment tool really free?
Yes. Every new account includes one free credit — enough to generate the complete assessment tool for UEPOPS075 — with no card and no subscription required. After that it's pay-as-you-go per unit.
Can I check my existing UEPOPS075 assessment instead of generating a new one?
Yes — upload your existing assessment or learner guide and Auditori maps it against every element, performance criterion, PE and KE of UEPOPS075, showing exactly what's covered and what's missing. Mapping costs a quarter of a credit.
Related units
- UEPOPS001 — Analyse single protection device operation
- UEPOPS002 — Apply environmental and sustainable energy procedures
- UEPOPS003 — Apply quality systems to work
- UEPOPS004 — Carry out operational checks on in-service electrical plant
- UEPOPS005 — Clean plant and equipment
- UEPOPS006 — Collect and analyse hydrological and meteorological data
- UEPOPS007 — Conduct chemical batching operations
- UEPOPS008 — Operate and monitor control room site in a multi-function environment
- UEPOPS009 — Conduct minor electrical maintenance
- UEPOPS010 — Conduct minor mechanical maintenance
- UEPOPS011 — Conduct multiple energy source isolation procedures for permit to work
- UEPOPS012 — Conduct non-routine operational testing